As for the christening - the girls did water play this afternoon in their kiddie pool. After they were done, they took a bath in the air tub. And at some point, Emily peed on the floor! Anyone know where we can find Backyardigan underwear for little girls? I think we could potty train her if we could find some "Pablo" underwear!
Saturday, July 11, 2009
Teased & Christened
Electricity was turned on yesterday evening and the air conditioning company showed up this morning to get the AC up and running. The upstairs unit had a leak and they didn't have enough freon to recharge it, so they got the downstairs up and running before they left, promising to be back "later". While the upstairs stayed hot, the downstairs unit cooled to a comfortable 80 degrees before it crashed. The AC unit wasn't draining, and when the condensation built up in the pan, the moisture sensor shut the system off.
Friday, July 10, 2009
We (almost) Passed!
Just a few items to fix before the inspector comes back out this afternoon. He let us slide on a few things (like not having the master bath vanity). The drop-off on the back side of the house is more than 30", so, as I type, David is installing a handrail along that edge. The electrical failed on a couple of items - no arc fault to the bedrooms (I caught that yesterday), water heater not connected (David's catch), no cover on the breaker box, and a loose ground wire to the meter. All small enough that since there is an electrician here fixing these, the inspector is going to call the power company to authorize power once he gets back to the office. He'll have to take pictures this afternoon when he comes back, then there's a bit of paperwork at the code office, and we'll be able to pick up our certificate of occupancy sometime next week!
Maybe I'll be able to sleep tonight without having nightmares of Richard Herrin (the head of the code office) coming out to nit-pick every detail during the final inspection!
Thursday, July 9, 2009
Electricians a No Show
Today's The Day
David is calling for the final inspection this afternoon. Best case scenario is that we get the CO (Certificate of Occupancy), have electricity turned on tomorrow and move in over the weekend, ending our 10 years of aggravation of dealing with the code office. A more realistic scenario is that we fail some minor items (I suspect we will fail plumbing since we don't have a vanity in the master bath), but that we can turn on electricity tomorrow, fix the items over the weekend and get the CO on Monday. And then there's the scenario that is keeping me up at night - the one where they say they won't give us a CO until the house is 100% finished - all doors installed, base molding in, kitchen cabinets complete, etc. That's another 3 months of David working full time to complete.
Tuesday, June 30, 2009
Cooktop Installed
Monday, June 29, 2009
Measure Twice, Cut Once
Thursday, June 25, 2009
Tuesday, June 23, 2009
Saturday, June 13, 2009
Kitchen Pictures for Jeff & Deanna to Drool Over
So, the kitchen is pretty much a clean slate - some rough framing for the island bar, and the duct for the kitchen vent.
This is one of two barrister's bookcases that David had. This one is being converted into a bookcase at the end of the island. Not sure what he'll do with the other one.
Here's one of the island cabinets - David was working on them two days before Katrina hit.
Here's the stainless steel table that we picked up at an auction years ago. Stainless - so no rust from Katrina.
On one of David's last trips to National Guard in Vicksburg, he came home with a walnut footboard. This will go above the cooktop,
So not so much to drool over yet - and that's why there haven't been any pictures!
This is one of two barrister's bookcases that David had. This one is being converted into a bookcase at the end of the island. Not sure what he'll do with the other one.
Here's one of the island cabinets - David was working on them two days before Katrina hit.
Here's the stainless steel table that we picked up at an auction years ago. Stainless - so no rust from Katrina.
On one of David's last trips to National Guard in Vicksburg, he came home with a walnut footboard. This will go above the cooktop,
So not so much to drool over yet - and that's why there haven't been any pictures!
Wednesday, June 10, 2009
2 Coats of Finish
David was hoping to apply the finish in the mornings and then work on kitchen cabinets in the afternoons but the finish is taking all day. No matter how well he cleans the applicator pads, some fuzz still ends up in the floor, which then needs to be sanded out before the next coat is applied. Plus the staircase takes more time. The first two coats are a Tung Oil/Resin product - Waterlox Original Formula. The next two coat will be the Satin Formula. The staircase may only need one more coat, but David will probably put another two coats on since he has to on the pine floors.
The floors are looking good - you can see the chatter marks from the drum sander, but it's not terrible. And certainly not so bad that I regret not spending the extra $4K to have it professionally sanded. It shouldn't be as noticeable with the satin finish. Once David is finished with the 4th coat, we need to stay off the floors for 24-48 hours, and then only light sock traffic for 7 days. Claire and Emily will just have to wait until next weekend to dance on the new shiny floors!
Sunday, June 7, 2009
Quick Update
David has finished sanding the floors, with a lot of help from Bobby. I've always heard about what a horrible mess the sanding makes, so I was pleasantly surprised that there wasn't inches of dust in the adjoining rooms. Still, I didn't realize that the walls would need to be vacuumed after sanding, so guess I can agree that the sanding does make quite a mess. Luckily we don't have any of the hanging light fixtures installed in the rooms with wood floors. On the plus side, we did get to try out the central vac. Worked great!
David will start applying the finish tomorrow. He's hoping for half days applying finish, with the remainder of the day spent on island cabinets. But he's going to put finish on the stairs at the same time, which may add a lot of time because of all the detail work.
Here's a link to a picture of the balusters we're going to copy on our staircase: http://www.stairwarehouse.com/56.html
David will start applying the finish tomorrow. He's hoping for half days applying finish, with the remainder of the day spent on island cabinets. But he's going to put finish on the stairs at the same time, which may add a lot of time because of all the detail work.
Here's a link to a picture of the balusters we're going to copy on our staircase: http://www.stairwarehouse.com/56.html
Wednesday, May 27, 2009
Wednesday, April 8, 2009
Lagniappe
The game room floor is in.

The first of the pocket doors (laundry room):
The laundry room door hardware:
The Sam's Club vanity, close-out sale mirror from a local electrical supply store, and sconces & faucets ordered on-line (these are in the girl's bathroom):
David's new massive ditch for hooking into the septic system:
And last (but not least), we received our "eviction" notice from FEMA - we need to be out by the end of April. Too bad we won't be into the house before the end of May!
Wednesday, April 1, 2009
First Railings & Doors
David has installed the upper balcony railng (minus the top piece). We bought just enough for this balcony so that we could see how the green balusters looked. David wanted black, but the price for the green was too good to pass up. They look good, so now we need to buy another 400. Another ebay good buy, at $1 per baluster and connector. Normal price is $2.25.
I keep forgetting to post a picture of the vinyl and lights under the house.
Saturday, March 21, 2009
Too much wood?
On one hand this is a great bonus because we'll be able to put more wood floors in for no additional cost. But it also means a delay in moving in since now David will be installing flooring upstairs that would have been carpeted by someone else. I suppose we could wait until after we move in, but it would be better to deal with the sanding before we move in.

The birds found a new nesting place - under the lower section of the front porch. Their nest is on top of a piling/below the decking. I was happy since I'll be able to lift the girls up so that they can see the eggs/baby birds. David's not thrilled since there are bolts and posts that he needs to install here!

Monday, March 9, 2009
Here's the deck at the top by the front door.
Subscribe to:
Posts (Atom)